Penjadwalan Berbasis Risiko dengan Program Evaluation and Review Technique untuk Mendukung Implementasi BIM 4D pada Proyek Jembatan
DOI:
https://doi.org/10.22487/renstra.v7i1.819Keywords:
BIM 3D, bridge construction, PERT, project duration, risk-based schedulingAbstract
The construction industry plays strategic role in national infrastructure development, particularly in bridge projects that are characterized by high complexity and significant implementation uncertainty. Bridges function not only as physical connections between regions but also as critical infrastructure supporting public mobility and economic growth. Therefore, accurate scheduling methods that are capable of accommodating the risk of time delays are required. This study to analyze the total project duration of bridge project risk-based approach through the integration of three-dimensional Building Information Modeling (BIM 3D) and the Program Evaluation and Review Technique (PERT). The analysis begins with the development of three-dimensional bridge structural model using Tekla Structures to generate bill of quantity that includes structural material volumes. These quantity data basis for probabilistic duration estimation using PERT method through expert judgment, which involves optimistic time, most likely time, and pessimistic time. The BIM 3D modeling results indicate total reinforcement steel volume of 24,343.4 kg and concrete volume of 274.1 m³. Furthermore, risk-based scheduling using the PERT method analyzed with the Precedence Diagram Method (PDM) produces total project duration of 190 days with completion probability of 50%. This result indicates potential risk of delay that should carefully project time control
Downloads
References
Y. Santi, N.A. Muhammad, and W.M.L. Ulwiyah, “Alternatif Perencanaan Jembatan Rangka Baja Dengan Menggunakan Metode LRFD di Jembatan Gelatik Kota Samarinda”, Rang Teknik Journal, vol. 4, no. 2, pp. 282-294, 2021. https://doi.org/10.31869/rtj.v4i2.2518
D. Hadicara and A. Rochim, “Penggunaan Metode PERT dan CPM dalam Proyek Pembangunan Jalan”, Pondasi, vol. 28, no. 1, pp. 32-44, 2023. https://dx.doi.org/10.30659/pondasi.v28i1.30148
R.A. Husna, N.F. Ilmiyah, and N.C. Resti, “Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat”, Journal Focus Action of Research Mathematic (Factor M), vol. 5, no. 1, pp. 97-109, 2022. https://doi.org/10.30762/f_m.v5i1.633
R.D.P. Ngestiaji, L.A.R. Winanda, and V. Aditama, “Penerapan Metode PERT Pada Penjadwalan Pembangunan Tugu Alun-Alun Kota Mojokerto”, vol. 3, no. 1, pp. 275-284, 2025. https://doi.org/10.56071/sintesi.v3i1.1579
R.R.P. Yudiyanto, L.A.R. Winanda, H.S.W. Sunarwadi, and D.K. Kartika, “Pemodelan 3D pada Bangunan Gedung Guna Mendukung Implementasi Bim 5D pada Proyek Konstruksi”, Jurnal Talenta Sipil, vol. 8, no. 2, pp. 555–562, 2025. https://doi.org/10.33087/talentasipil.v8i2.877
S. Wahyudiono, F. R. Andardi, Y. Rusdianto, and R. Awalludiensyah, “Penerapan Metode Program Evaluation and Review Technique (PERT) Pada Proyek Malang Creative Center (MCC) Berdasarkan Building Information Modelling (BIM)”, Jurnal Media Teknik Sipil, vol. 21, no. 2, pp. 66-76, 2023, https://doi.org/10.22219/jmts.v21i2.28969
A. Sholichan and A.E. Husin, “Optimization of M-PERT and BIM 5D to Minimize the Risk of Time Delay and Overrun in Stadium Project Structure Works: Key Success Factors”, International Journal of Research and Review, vol. 8, no. 7, pp. 491-498. https://doi.org/10.52403/ijrr.20210770
M.Y. Ramawan, L.A.R. Winanda, V. Aditama, M. Wijayaningtyas, and D. Kartika, “The effectiveness of BIM implementation in high-rise building”, AIP Conferfence Proceeding, vol. 3110, no. 1, p. 1-14, 2024. doi: 10.1063/5.0205185. https://doi.org/10.1063/5.0205185
D. Sabil and Erizal, “Penerapan Buidling Information Modeling (BIM) 5D pada Proyek Gedung Simpang Temu Dukuh Atas, Jakarta Pusat”, Jurnal Teknik Sipil dan Lingkungan, vol. 8, no. 2, pp. 95-104, 2023. https://doi.org/10.29244/jsil.8.02.95-104
D. Maula Al Farizi and K. Hapsari, “Evaluasi Metode Perhitungan Tulangan Kolom Dengan Software Tekla Structures dan Autodesk Revit”, Construction Material Journal, vol. 7, no. 1, pp. 45-50, 2025. https://doi.org/10.32722/cmj.v7i1.7066
A.T. Handayani, E. Budiman, and T. Rahman, “Penerapan Building Information Modelling (BIM) dalam Menghitung Quantity Take Off Material Struktur (Studi Kasus: Proyek Gedung Rumah Sakit Mata di Jl. M. Yamin, Kota Samarinda, Kalimantan Timur)”, Teknologi Sipil: Jurnal Ilmu Pengetahuan dan Teknologi, vol. 8, no. 1, pp. 48, 2024. http://dx.doi.org/10.30872/ts.v8i1.16024
A.M.A. Hafiz, A. Firmansyah, and N. Lastriana, “Application of Building Information Modeling in the Construction of the Parakan Lima Bridge in Purwakarta Regency”, Potensi: Jurnal Sipil Politeknik, vol. 27, no. 2, pp. 64-71, 2025. https://doi.org/10.35313/potensi.v27i2.4024
F.A. Rozy and R.G.W. Ode, “Manajemen Waktu, Biaya dan SDM Proyek Konstruksi pada Pembangunan Gedung Ruang Kuliah Fia Universitas Brawijaya Malang dengan Menggunakan Metode PERT dan PDM”, Media Teknik Sipil, vol. 12, no. 1, pp. 1-10, 2014.
Y. Ambalinggi, L. Sriwahyuni, S. Norhidayanti, and F. Oktavia, “Analysis Use of PERT-CPM: Optimizing Manufacturing Production Process Resources for Building Construction Projects on Kunjang River Region, East Kalimantan”, Jurnal Teknik, vol. 2, no. 3, pp. 1283-1291, 2024.
M.R.A. Simanjuntak, “Rekomendasi Hasil Analisis Waktu Pelaksanaan Lingkungan Kota Serang Provinsi Banten”, Jurnal Ilmiah Media Engineering, vol. 4, no. 4, pp. 219-228, 2014.
F.R. Andardi, “Analisis Penerapan Sistem Penjadwalan dengan Metode PERT pada Proyek Konstruksi (Studi Kasus: Rehabilitasi dan Peningkatan Infrastruksi Pasar Tradisonal Kota Malang)”, Prokons Jurusan Teknik Sipil, vol. 14, no. 2, pp. 19-24, 2021.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 REKONSTRUKSI TADULAKO: Civil Engineering Journal on Research and Development

This work is licensed under a Creative Commons Attribution 4.0 International License.





This work is licensed under a 