Rescheduling Proyek Pembangunan Jembatan Palu V Menggunakan Microsoft Project

Authors

  • Aslam Aslam Jurusan Teknik Sipil, Fakultas Teknik Universitas Tadulako, Jl. Soekarno-Hatta Km 9, Palu 94118, Indonesia
  • T.M. Kamaludin Jurusan Teknik Sipil Universitas Tadulako, Jl. Soekarno Hatta Km. 9 Palu 94118, Indonesia

DOI:

https://doi.org/10.22487/renstra.v2i1.238

Keywords:

scheduling, project, Microsoft Project

Abstract

One form of project planning is Project scheduling. Project scheduling is one of the elements of Project planning results, which can provide information on the relationship of each other activity to the entire project, the identification of relationships that must be precedence between activities, showing realistic cost and time estimates for each activity on project completion. In this research the author plans to process project work activity of the Palu V Bridge development by limiting its job stage to the quality of concrete work of FC ' 30MPa for the building over the floor plate. This type of research is analytic. Data collection in the form of secondary data such as schedule and RAB is done by requesting directly the required data to the relevant party. Then conducted initial schedule evaluation, followed by using Microsoft Project 2019 tool as processing result of the project Process Bridge Hammer V. From the results of the study it was concluded that process use Microsoft Project 2019 requiring a duration of 199 working days. While the scheduling is carried out in the field, the executor requires a duration of 366 working days and the planned scheduling of the implementing party takes 167 working days. If compared to the results of scheduling time duration with the implementation of the field and the duration of the execution planner, the results obtained by the researcher more than 167 days from the time of implementation in the field and slower 32 days from the duration of the planning time.

Downloads

Download data is not yet available.

References

I. Agustiar and R. Handrianto, “Evaluasi Penjadwalan Proyek Menggunakan Metode CPM dan Kurva S”, Wahana Teknik, vol. 7, no. 2, p. 99, 2018.

N.M. Jaya dan A.A.D.P. Dewi, “Analisa Penjadwalan Proyek Menggunakan Rankedpositional Weight Method dan Precedence Diagram Method”, Jurnal Ilmiah Teknik Sipil, vol. 11, no. 2, 2007.

Fedrikson, M. Jamal, and F.N. Abdi, “Optimalisasi Biaya dan Waktu Pelaksanaan Proyek Pada Proyek Dengan Metode Least Cost Analysis”, Jurnal Teknologi Sipil, vol. 3, no. 1, p. 21, 2019.

T. Tarliah and A. Dimyati, Operations Research : Model-Model Pengambilan Keputusan, Bandung : Sinar Baru Algesindo, 2011.

A.Maddeppungeng, I. Suryani, and M. Iskandar, “Analisis Pengendalian Penjadwalan Pembangunan Gedung Administrasi Universitas Pendidikan Indonesia (UPI) Kampus Serang Menggunakan Metode Work Breakdown Structure (WBS) dan Kurva-S”, Jurnal Fondasi, vol. 4, no. 1, p. 88, 2015.

Fachrurrazi, Microsoft Project 2010: Bahas Tuntas Dengan Ribbon, Yogyakarta: Deepublish, 2018.

P. Kelana, Optimalisasi Penggunaan Sumber Daya Manusia Dengan Metode Resource Leveling Menggunakan Bantuan Microsoft Project 2007, Surakarta: Fakultas Teknik Jurusan Teknik Sipil Universitas Sebelas Maret, 2010.

A. Kusrianto, Panduan Lengkap Memakai Microsoft Project 2007, Jakarta: PT. Elex Media Komputindo, 2008.

G.D. Wijaya, Studi Kasus Penjadwalan Proyek Pada Proyek Rumah Toko X Menggunakan Microsoft Project 2010, Surabaya: Fakultas Teknik Jurusan Teknik Sipil Universitas Kristen Petra, 2010.

N.I.M. Muliyadi, Penjadwalan Ulang Proyek Konstruksi Dengan Preseden Diagram Method (PDM) (Studi Kasus Pembangunan Pembangunan Unit Sarana Belajar TK Pembina Kabupaten Kecamatan Johan Pahlawan Kabupaten Aceh Barat), Aceh: Universitas Teuku Umar Meulaboh, 2016.

A. Rezky, Reschedulling Proyek Konstruksi Dengan Menggunakan Software Penjadwalan (Reschedulling Construction Project With Software For Schedulling) (Studi Kasus: Proyek Pembangunan Jalan Nasional Bugel-Galur-Poncosari Tahap 1, Kabupaten Bantul, Yogyakarta: Universitas Islam Indonesia, 2018.

M.I. Setiawan, “Rescheduling Waktu Pekerjaan Guna Optimasi Biaya Pembangunan Rusunawa Siwalan Kerto Surabaya”, Neutron, vol. 9, no.1, p. 20, 2009.

S. Tamba and D.M. Hutauruk, “Optimasi Biaya Dan Waktu Akibat Penjadwalan Ulang Pada Proyek Perumahan Menggunakan Microsoft Project”, Journal of Civil Engineering, Building And Transportation, vol. 2, no. 1, p. 34, 2018.

Widiasanti, Irika, and Lenggogeni, 2013, Manajemen Konstruksi, Bandung: PT Remaja Rosdakarya, 2003.

S. N. Pratama, “Rescheduling Waktu Pelaksanaan Proyek Pada Pembangunan Gedung SMA Unggulan Samarinda Provinsi Kalimantan Timur”, Teknik Sipil dan Arsitektur, vol. 1, no. 1, p. 733, 2016.